Freedom Tower Construction Finally Begins

(Portions from Wikipedia)

Rebuilding at the World Trade Center site in Lower Manhattan began this week, nearly 4 and a half yars after the Twin Towers were destroyed by the worst terrorist attack in American history. The project had been delayed due to acrimonious disputes over money, security and design but the last major issues were resolved on April 26th, 2006 with a deal between developer Larry Silverstein and the Port Authority of New York and New Jersey.

The site will include three other high rises plus a residential tower that will surround a memorial, museum and cultural center dedicated to what relatives of the September 11 victims consider a sacred site.

Construction is scheduled to be finished by 2011 or 2012. As reported by the developers of the Freedom Tower, the skyraper will rise 1368 feet into the air.

More information (source LMDC):

Freedom Tower Construction Fact Sheet

Developer: World Trade Properties LLC
Construction Manager: Tishman Construction Corp.
Architect: Skidmore, Owings & Merrill, LLP

On April 27 at approx. 8:30am, the construction team will
mobilize into the World Trade Center site, marking the beginning
of construction of the Freedom Tower. The following activities
will take place over the next month:

  • Mobilize heavy equipment: excavators, drilling equipment,
    rock breaking equipment, hoe rams, backhoes, rock drills, track
    loaders
  • Deliver and install perimeter barriers
  • Survey and layout excavation for foundations
  • Install safety protection and barricades throughout the work
    area
  • Install scaffold stair towers from street level to foundation
    level
  • Begin excavation of the slab, general excavation
  • Begin rock drilling for footings
  • Begin layout of trackside barriers, install barrier wall
  • Mobilize and prepare for construction of tower foundations

Utility Relocation work along PATH Tracks
Contractor: Petrocelli Electric
Construction Start on Site: Surveying and layout
work started in March, construction work started in April.

Duration of Work: 6 to 8 months
Scope of Work: Primarily electrical utility relocations
of PATH utilities that interfere with the tower foundations. Work
will be performed at track level around the PATH tracks mostly
on off hours nights and weekends.

Excavation and Foundation Construction Work

Contractor: Laquila Group Inc.

Construction Start on Site: April 27, 2006
Duration of Work: 10 to 12 Months
Scope of Work: Excavation of rock for the construction
of tower footings. Construction of tower foundations consisting
of concrete spread footings on rock, rock anchors and mini-caissons.
Work will occur both during regular hours and off hours for the
track area work.